Planning and Construction Stages

Stage 1

(August 1999- September 2000)

Aug 99-May 2000. Services held in the bomb shelter, planning, fund raising and permits for a temporary structure to be built on our lot COMPLETED
May-Aug 2000 Purchase of temporary structure including developement of outdoor space (1200-1500 Sq. ft.)PURCHASE COMPLETED - DEVELOPMENT UNDERWAY
September 1, 2000 Kindergarten/nursery opens, high holidays services held in new temporary building KINDERGARTEN OPENED IN SEPTEMBER 2002

 

Stage 2

(2001- 2003)

2001-2002 Planning for a permanent building, fund raising and reassessment of needs
2003 Corner stone for permanent building (4,000-5,000 sq. ft)

Budget

Stage 1 Planning of temporary structure COMPLETED  
Infrastructure $30,000
Purchase of Temporary Building COMPLETED  
Interior needs NEARING COMPLETION $10,000
Total for Stage 1 $40,000
 
     
Stage 2 Planning $60,000
Building (500 meters) $750,000
Interior needs $100,000
Total for Stage 2 $910,000
     
  Total for Stage 1 and 2 $950,000

 

Help us move from "Stage 1"

In the past we had been relegated to an underground bomb shelter, now we have a temporary  home for services and other community activities!

Help us to build a permanent synagogue for our community in Tzur Hadassah.

Shalom and Thanks.